Colossus Minerals Inc

Colossus Minerals : High Grade Noble Metals Projects in Brazil SPD-034 intersected 20.44 metres at 158.82 g/t gold, 67.14 g/t platinum and 101.10 g/t palladium
NEWS!!!
over 11 years ago
9

Colossus Minerals’ Development Remains On Schedule forInitial Production In Second Half of 2013

Toronto, Ontario, February 7, 2013 – Colossus Minerals Inc. (the “Company” or “Colossus”)(TSX: CSI)(OTCQX:COLUF) is pleased to provide a development update for its 75% owned Serra Pelada gold-platinum-palladium Mine. The Serra Pelada Mine is a joint venture between Colossus and Cooperativa de Mineração dos Garimpeiros de Serra Pelada (“COOMIGASP”) located in the State of Pará, Brazil.

Highlights

 The Company remains on track to start initial production early in the second half of 2013 at an initial rate of 250 tonnes per day (“tpd”) and continue the ramp up phase throughout the remainder of 2013 to 500 tpd. The current plan envisages two active mining faces for 250 tpd of production, three to five mining faces for 500 tpd of production and six to nine mining faces for 1,000 tpd of production. The Company expects to achieve 1,000 tpd of production by the end of the first quarter of 2014.

 Underground development is progressing well with a number of infrastructure projects necessary to support full-scale mining now complete or well underway. Development at the face continues through the mineralized zone.

 The rock quality during collection of the bulk sample remains within expected parameters from geotechnical work completed prior to first access to the mineralized zone. The Company continues with systematic and cautious development as this is the first time accessing the mineralized zone and it is providing valuable geotechnical information ahead of initial production.

 Dewatering is progressing well from both surface and underground while dewatering of the historic pit to within five metres of the solids level is 95% complete. Underground water inflow rates remain within expectations.

 Process plant construction remains on schedule for commissioning to begin early in the second half of 2013; the total project is currently 60% complete. More than 95% of engineering & procurement is complete, 55% of concrete has been poured and structural steel erection will commence by the middle of February.

 Other critical infrastructure construction also remains on schedule. The power line and power house are on track to be commissioned early in the second quarter of 2013 while the tailings dam is expected to be ready in conjunction with mill commissioning.

Claudio Mancuso, Chief Executive Officer commented, “We are now within six months of commencing our commissioning phase. Both underground development and infrastructure construction are progressing well towards our initial production target of early in the second half of 2013. Going forward, the Company will provide development updates monthly so that construction and development progress can be tracked as we strive towards our most important milestone; production at Serra Pelada.”

David Anthony, President & Chief Operating Officer further commented, “Mobilization of the site construction team is now advanced. All principle materials and resources are in place to enable completion of the process plant and infrastructure projects as scheduled. Our mining team is pleased to have started collection of the bulk sample. Planning and preparations have been made to start mining operations during the third quarter of this year.”

Construction and Development at the Serra Pelada Project

Underground Development

As announced on December 31, 2012, the Company reached mineralization in its secondary development and the bulk sample collection process is ongoing with all material being assayed and sorted on surface on the stockpile pad. Geologic controls and assaying of material continue to guide the bulk sampling process. Ground conditions and ground water flow into the mine remain manageable.

Development of this secondary access will continue and management expects extraction and sampling of the bulk sample to be complete in the first quarter. The Company is progressing cautiously and prudently, as the bulk sample process is also being used to collect comprehensive geotechnical information and to test different extraction methods. Geotechnical assessment and monitoring indicates that full scale mining operations will be sustainable at planned rates of production.

Underground development is now ramping up and focusing on the development of infrastructure necessary to support initial production early in the second half of 2013. In addition to developing the main decline while developing the bulk access drive, a number of infrastructure projects are well underway or completed. Two new drill bays have been established in the bulk-sample access drive,allowing the Company to drill much shorter holes (maximum total length of 150 metres) resulting in better targeting of the areas the Company plans to include in its first resource/reserve estimate at the beginning of the second quarter of 2013. These drill bays are also being used to gather geotechnical information which will be used in the development of the Company’s mine plan.

Former drill bays have now been converted into permanent underground infrastructure to support mining operations. The first underground drill bay has been converted into an electrical substation and a former sump has been converted into a second electrical substation. The second underground drill bay has been converted into a refuge station which was commissioned in January 2013. Work continues on the refurbishment of an artisanal shaft which will be used to provide underground ventilation. This shaft will be enlarged in the second quarter of 2013 and the ventilation system will be upgraded to support expansion of mining operations.

The Company also continues to develop its mine plan. While the geological and geotechnical information gathered during the collection of the bulk sample is yet to be incorporated, the Company believes its ramp-up plans are conservative and achievable. The Company is currently planning anadditional 600 metres of development between now and the end of June in order to start initial production at 250 tpd in the second half of the year. This estimate assumes a development rate of three

metres per day per development crew. During 2012, the Company achieved improvements in rates of

advance as additional equipment and more experienced underground mine personnel were mobilized

to site. Development rates for the period from January to July 2012 were two metres per day however

an average of three metres per day was consistently achieved during the period from August 2012 to

January 2013.

In February and March, the Company will have one development crew and will ramp to two in April once ventilation upgrades have been made and additional mining equipment, scheduled for March delivery, arrives on site. Initial production will begin from two active mining faces and the Company

anticipates having a 10,000 tonne stockpile once production begins in the second half of 2013. Ramp-up

activities will continue throughout the remainder of 2013 as the Company anticipates having four

development crews by August and expects to be at 500 tpd by the fourth quarter of 2013 and 1,000 tpd

by the end of the first quarter of 2014. The current plan envisages two active mining faces for 250 tpd

of production, three to five mining faces for 500 tpd of production and six to nine mining faces for 1,000

tpd of production. Geotechnical information gathered during the bulk sample process suggests that

these production rates may be achievable with less active mining faces than currently planned and the

additional 600 metres of development between now and the end of June in order to start initial

production at 250 tpd in the second half of the year. This estimate assumes a development rate of three

metres per day per development crew. During 2012, the Company achieved improvements in rates of

advance as additional equipment and more experienced underground mine personnel were mobilized

to site. Development rates for the period from January to July 2012 were two metres per day however

an average of three metres per day was consistently achieved during the period from August 2012 to

January 2013.

In February and March, the Company will have one development crew and will ramp to two in April

once ventilation upgrades have been made and additional mining equipment, scheduled for March

delivery, arrives on site. Initial production will begin from two active mining faces and the Company

anticipates having a 10,000 tonne stockpile once production begins in the second half of 2013. Ramp-up

activities will continue throughout the remainder of 2013 as the Company anticipates having four

development crews by August and expects to be at 500 tpd by the fourth quarter of 2013 and 1,000 tpd

by the end of the first quarter of 2014. The current plan envisages two active mining faces for 250 tpd

of production, three to five mining faces for 500 tpd of production and six to nine mining faces for 1,000

tpd of production. Geotechnical information gathered during the bulk sample process suggests that

these production rates may be achievable with less active mining faces than currently planned and the

Company is in the process of testing different extraction methods in the bulk sample access drive prior

to incorporating these results into its preliminary mine plan.

All equipment required to achieve the development and mining rates discussed above have been

ordered and are on their way to site. Three new Atlas Copco scoop trams and two haulage trucks will be

delivered to site by mid-March. Two other haulage trucks will be delivered in May and August,

respectively. A third rockbolter will arrive at site in June and a fourth jumbo in July.

Process Plant Construction

Process Plant construction remains on schedule for commissioning to begin early in the second half of

2013; the total project is currently 60% complete. The various phases of the processing plant

construction, along with respective percentage completion, are presented in the table below.

Engineering 95%

Procurement 95%

Ball mill refurbishment 95%

Earthworks 95%

Civil Construction 55%

Structural Steel Fabrication 25%

Structural, Mechanical, Piping & Electrical Installation Contract awarded Civil construction is progressing well and has not been significantly impacted by the seasonal rainfall.

Concrete placement is ahead of schedule at 55% complete and this team is fully mobilized, with completion scheduled for mid-April. Sub-grade concrete placement is complete for all process plant buildings and structures and above grade concrete is progressing slightly ahead of schedule. Structural steel for the process plant will begin to arrive by the middle of February and steel erection will begin shortly thereafter. Ball mill refurbishment will be complete in early February with delivery to site expected in early March. Critical contracts for structural steel, plate work, piping fabrication and

structural, mechanical, electrical and instrumentation installation have been awarded and site

establishment is advanced.

Critical process plant equipment continues to be delivered to site. The tailings thickener was delivered to site in December 2012. The in-line leach reactors, gravity concentrators vibrating screens, vibrating feeder, hydrocyclones and reagent dosing pumps are landed at the port and will be delivered during February.

A pictorial update has also been provided with this press release (and can be accessed by clicking here) to provide additional information regarding the progress of the processing plant and other infrastructure construction.

Infrastructure Construction

The 34.5 kV transmission line to bring power to site is currently under construction by Equatorial Energia S/A (“EE”), Brazil’s second largest utility company, and is on track to be commissioned by early April. The power house to connect the site distribution lines to the EE transmission line is currently under civil works construction. Concrete placement and structural steel erection for the power house is substantially complete. Mechanical installation is scheduled to start in the middle of February. This facility will be available for use by the end of March. The power house will also be equipped with generators for backup power, which have already been purchased and are on site.

Basic engineering for the tailings dam is complete. Golder Associates are in the process of completing detailed engineering. The earthworks contract has been awarded and this contractor is mobilized to site.

Bulk materials for construction are currently being procured and will begin to arrive in the middle of February. The tailings impoundment facility is on track to be ready to receive material by the end of July.

Dewatering

Dewatering activities from surface have proceeded for more than 18 months and the rate of water removal remains consistent. As development has continued into the mineralized zone, our underground dewatering has increased and is now in balance with the rate of production from surface. Dewatering activities remain manageable and these are integrated with the ground control program. Lastly, the water level in the historic pit has been drawn down by approximately twenty metres.

The Company’s plan is to dewater to within five metres of the solids level and this is now 95% complete.

Please login to post a reply
SMF069
City
Downtown Core, TO
Rank
President
Activity Points
40296
Rating
Your Rating
Date Joined
02/25/2008
Social Links
Private Message
Colossus Minerals Inc
Symbol
CSI
Exchange
TSX
Shares
214.8M (fully diluted)
Industry
Metals & Minerals
Create a Post