I read in the other QEC bullboard that there is a current shortage of fraccers so Talisman wants to fracture Gentilly, Leclecrville, and Fortierville in sequence for logistical reasons.

Well Name Spud Date Finish Date Duration Spent on Site

Gentilly December 13, 2009 January 22, 2010 1 month 8 Days

Leclercrville January 29, 2010 March 29, 2010(?) projected 2 months

Fortierville March 29, 2010(?) May 29, 2010(?) projected 2 months

2 horizontal fracs would take about 6 weeks. (big guess)

The first frac will have to begin (May 29 - 6 weeks) = April 15, 2010

Please login to post a reply
wblue
City
Rank
Treasurer
Activity Points
443
Rating
Your Rating
Date Joined
01/31/2008
Social Links
Private Message
Questerre Energy Corporation
Symbol
QEC
Exchange
TSX
Shares
291,324,457 Oct17/2016
Industry
Energy & Environment
Website
Create a Post